Delivery Scheduling and Transportation Scheduling:
Shipping activities and Transportation can be scheduled automatically in sales documents. There are two different type of scheduling: Delivery Scheduling and Transportation Scheduling.
Configuration:
- Define Scheduling by Sales document Type
SaTy DlvSchl TrasSchl Backwardschl
OR X Select Select
Options for Delivery Scheduling: Space – Shipping scheduling Off
A – Shipping scheduling delivery order (w/o loading time)on
X – Shipping Scheduling on

Select the order type and specify whether you want to carry out delivery scheduling and transportation scheduling. You can also specify that for a particular Order type only Backward scheduling is carryout. (generally if required qty is not available on requested date, system carryout Forward scheduling).

When you specify Delivery scheduling, the system automatically determine Pick/Pack time and Loading time for each schedule line, according to the shipping point for which an item is shipped. The system uses Pick/Pack time and loading time to help determine the material availability date and the loading date respectively.

For each shipping point, system can – Propose default for the pick/pack time and loading time or Determine more precise time by taking other factor into account. (route, loading group, weight group).

When you specify Transportation scheduling, the system proposes Transportation lead time and Transit time for each schedule line. These times are determined by route. The system uses the transportation lead time and transit time to help determine the transportation planning date and the goods issue respectively.
Time how determined Helps to Determine
Pick/Pack time Shipping Point Mat. Availability Date
Loading Time Shipping Point Loading date
Trans. Lead time Route Trans. Planning date
Transit Time Route Goods Issue date.

- Define Scheduling By Shipping Point
For each shipping point provide following details:
Factory Calendar:
Working times:
Determine Load Time: Space – No Loading time determination.
A – Route Dependent
B – Route Dependent (Route ‘ ‘)
C – Default from shipping point
Det. Pick/Pack time: Space – No pick/pack time determination.
A – Route Dependent
B – Route Dependent (Route ‘ ‘)
C – Default from shipping point
Rounding Working Days: As buffer time.

- Maintain duration: here we can maintain all the above time for shipping point and Route.
First we have to make setting in shipping point how the Load time and pick/pack time will be determined. Suppose we select C (Default from shipping point) than it will ask to enter the time also in the same screen. If you select other option than C (means based on route) we can maintain the pick/pack time over here.
Double click on “Pick/Pack time” and provide details as below;
Shipping Point ---Route---WgtGRp---Pick/pack days----PP hours
CYSP 000002 0001 1 15

Double click on “Loading Time” and provide following details:
Shipping Point---route----Load GRP----Load time Days ----L.time hours
CYSP 000002 0001 1 10

Double Click on “Route” and fill below details for the specific route:
Transit duration days Transit dur. Hrs TransLedTimeDays TransLedTimeHrs

2 comments:

  1. We would like to acknowledge the exceptional service that we received during the entire refinancing process. Mr Lee professionalism and knowledge of the loan company was impressive and truly appreciated. Mr Lee is a reliable loan officer.In the past, we have had experience with several others banks and have found the process frustrating and tedious. Mr Lee went above and beyond to ensure that all of our needs were met and that everything was handled thoroughly and efficiently. We have and will continue to recommend him in the future.”Mr Lee Contact Email /Whatsapp 247officedept@gmail.com+1-989-394-3740